2nd August 2007. The builders have more or less finished leaving the remaining work for volunteers. The heating system has been tested and electrical system and fire alarm are installed. The first fix is completed for the alarm and CCTV and will be completed soon. The floor covering in the main hall, small room and main entrance is being laid from 21st to the 24th August. (images to follow soon)

28th June 2007. The following progress has been made. Heating system and most of plumbing installed. Kitchen 90% fitted with more progress expected weekend 29th/1st. Store room at one end of hall and stage at the other well under way by Tomas/Dave & Roy. Doors being fitted. Go ahead given to Delta Alarms to install alarm system and CCTV to be commissioned by 13th July.

15th June 2007. Progress being made with tiling of kitchen and toilets. Heating system (oil) being installed and painting of kitchen/hall and toilets progressing well. Materials for stage ordered from Huws Gray for delivery 18th June and hopefully voluteers will work on this during week 18th-22nd.

7th June 2007 Beams being given a coat of black by volunteers working on the gantry supplied by Ellis

4th June 2007. Ceiling of main hall given its first coat of white emulsion by Roy, Dave, Tomas, Chris & Ken

2nd June 2007. Since the last item posted in March there has been considerable progress. The first fix electrical rewiring has been completed. Similarly for the first fix plumbing. The plasterers have almost completed their work and by tuesday 5th June the ceiling of the main hall will be available for painting by volunteers from the community. The kitchen floor tiles will be laid by the 8th June followed on the 9/10th by the kitchen.

Images from around the time of scaffolding removal and plastering being started during the latter part of May 07

 

29th March. Windows being fitted. Lovely craftsmanship by Coeden Joinery of Niwbwrch

 

Tiles being fitted on 23rd March 2007.by Ogwen Roofing of Niwbwrch

*****

Images taken

22nd March 2007

*****

Photo's taken on 8th March 2007

Two show the new tiling

&

Two show the progress with the stone cladding

*****

The following 15 pictures taken during site visit on 20th Feb. 2007

Real stone cladding - new build
View of roof before tiling
This will be disabled toilet
THis will be the kitchen
Toilet area again
Main hall - roof void
Roof void
View into kitchen from hatch
Kitchen
Roof void -small room
Looking from stage end
This will be an entrance
Another view of cladding
Small room towards stage door
An attractive alcove in main hall

 

*****

Pictures taken of the latest roof work just before dusk on the 10th Feb. 2007

Roof insulation can be seen between the vertical laths

 

Photo's taken on a Spring like day, 3rd Feb. 2007

Ogwens roofing now on site and have removed all the old slates from the rear of the building ready for re fitting during the week 5th Feb.

Roof timbers for the extension now completed and ready for fitting slates

 

New roof timbers being fitted on 24th Jan 2007

 

Progress on 20th Jan. 2007

 
   

-------------------------------------------

 

Site meeting held on 20th December 2006

Representatives of RGR, Ellis Williams and Criw Niwbwrch were present

Work is on schedule for handing over in Feb. 2007

Roofing work to begin early Jan. 2007

 

 

Pictures taken on 23rd Nov. show latest progress with roof work to begin soon.

23rd Nov. 2006
23rd Nov. 2006

Link to plan of completed building

Concrete floor down in kitchen/toilet area (11th) & walls nearly completed (16th)

 
 
11th Nov. 2006
11 Nov. 2006
16 Nov. 2006
16 Nov. 2006

 

  The other porch demolished, footings in & soil moving by 'Jacko'
   
26th Oct. 2006
28th Oct 2006
26th Oct. 2006
26th Oct. 2006

 

  Progress on the 24th & the porch has gone

 

24th Oct. 2006
24th Oct. 2006
24th Oct. 2006

 

It's a big day for Criw Niwbwrch. The contractor has moved on site.

 

23rd Oct. 2006
23rd Oct.2006
23rd Oct.2006
23rd Oct.2006

--------------

 

The local contractor selected to carry out the building work on ''Eglwys Bach'' is

J Ellis Williams & Son Ltd (Rhosneigr)

The contract is scheduled to begin on 16th Oct. 2006 with erection of scaffolding on the 23rd Oct..

--o--

The roofing part of the contract has been given to

E & M Ogwen Roofing Contractors (Niwbwrch)

 

--o--

The Architects for the Project are

R.G.R Partnership (Llangefni)

 

 