2nd
August 2007. The
builders have more or less finished leaving the remaining work for
volunteers. The heating system has been tested and electrical system
and fire alarm are installed. The first fix is completed for the
alarm and CCTV and will be completed soon. The floor covering in
the main hall, small room and main entrance is being laid from 21st
to the 24th August. (images to follow soon)
28th
June 2007. The
following progress has been made. Heating system and most of plumbing
installed. Kitchen 90% fitted with more progress expected weekend
29th/1st. Store room at one end of hall and stage at the other well
under way by Tomas/Dave & Roy. Doors being fitted. Go ahead
given to Delta Alarms to install alarm system and CCTV to be commissioned
by 13th July.
15th
June 2007. Progress
being made with tiling of kitchen and toilets. Heating system (oil)
being installed and painting of kitchen/hall and toilets progressing
well. Materials for stage ordered from Huws Gray for delivery 18th
June and hopefully voluteers will work on this during week 18th-22nd.
7th
June 2007 Beams
being given a coat of black by volunteers working on the gantry
supplied by Ellis
4th
June 2007.
Ceiling of main hall given its first coat of white emulsion by Roy,
Dave, Tomas, Chris & Ken
2nd
June 2007.
Since the last item posted in March there has been considerable
progress. The first fix electrical rewiring has been completed.
Similarly for the first fix plumbing. The plasterers have almost
completed their work and by tuesday 5th June the ceiling of the
main hall will be available for painting by volunteers from the
community. The kitchen floor tiles will be laid by the 8th June
followed on the 9/10th by the kitchen.
|
|
|
|
Images
from around the time of scaffolding removal and plastering
being started during the latter part of May 07 |
|
|
|
|
29th March.
Windows being fitted. Lovely
craftsmanship by Coeden
Joinery of Niwbwrch
|
|
|
|
Tiles being fitted
on 23rd March 2007.by Ogwen
Roofing of Niwbwrch
|
|
|
|
*****
|
Images
taken
22nd
March 2007
|
|
|
|
|
*****
|
Photo's taken
on 8th March 2007
Two show the
new tiling
&
Two show the
progress with the stone cladding
|
|
|
|
*****
The following
15 pictures taken during site visit on 20th Feb. 2007
|
|
|
Real
stone cladding - new build |
View
of roof before tiling |
This
will be disabled toilet |
|
|
|
THis
will be the kitchen |
Toilet
area again |
Main
hall - roof void |
|
|
|
Roof
void |
View
into kitchen from hatch |
Kitchen |
|
|
|
Roof
void -small room |
Looking
from stage end |
This
will be an entrance |
|
|
|
Another view of cladding |
Small room towards stage door |
An attractive alcove in main hall |
*****
|
|
|
Pictures
taken of the latest roof work just before dusk on the
10th Feb. 2007
Roof
insulation can be seen between the vertical laths
|
|
Photo's taken on a Spring like day, 3rd
Feb. 2007
Ogwens roofing now on site and have removed
all the old slates from the rear of the building ready
for re fitting during the week 5th Feb.
Roof timbers for the extension now completed
and ready for fitting slates
|
|
|
|
New roof timbers being
fitted on 24th Jan 2007
Progress on 20th Jan.
2007
-------------------------------------------
|
|
|
Site
meeting held on 20th December 2006
Representatives
of RGR, Ellis Williams and Criw Niwbwrch were present
Work
is on schedule for handing over in Feb. 2007
Roofing
work to begin early Jan. 2007
|
|
|
|
|
|
|
Pictures
taken on 23rd Nov. show latest progress with roof work to begin
soon.
|
|
23rd
Nov. 2006 |
23rd
Nov. 2006 |
Link
to plan of completed building
Concrete floor down in
kitchen/toilet area (11th) & walls nearly completed (16th)
| |
|
|
|
|
| |
11th
Nov. 2006 |
11
Nov. 2006 |
16
Nov. 2006 |
16
Nov. 2006 |
| |
The other
porch demolished, footings in & soil moving by 'Jacko' |
| |
|
|
|
|
|
26th
Oct. 2006 |
28th Oct 2006 |
26th
Oct. 2006 |
26th
Oct. 2006 |
| |
Progress on
the 24th & the porch has gone |
|
|
|
24th Oct. 2006 |
24th Oct. 2006 |
24th Oct. 2006 |
|
It's
a big day for Criw Niwbwrch. The contractor has moved on site. |
|
|
|
|
23rd
Oct. 2006 |
23rd
Oct.2006 |
23rd
Oct.2006 |
23rd
Oct.2006 |
--------------
The local
contractor selected to carry out the building work on ''Eglwys Bach''
is
J
Ellis Williams & Son Ltd (Rhosneigr)
The contract
is scheduled to begin on 16th Oct. 2006 with erection of scaffolding
on the 23rd Oct..
--o--
The roofing
part of the contract has been given to
E
& M Ogwen Roofing Contractors (Niwbwrch)
--o--
The Architects
for the Project are
R.G.R
Partnership (Llangefni)